Backup Copy Job Wizard: STEP 3
文章分類:
Disabling Scheduled Job Execution
If you want to start the job manually (without any schedule), select the Do not schedule, run on demand check box:
Daily Backup
To run a job once a day, do the following:
Choose Run daily/weekly from the schedule drop-down list:
- Specify the time when the job should be started in the Starting field.
- Specify the end time for the job in the Ending field. If the job has not completed by the time specified, the job will be stopped.
- Choose a time zone which should be used for the job start and end times from the time zone drop-down list.
- Select the days of the week during which the job will be started.
Monthly or Yearly Backup
To run a job monthly or yearly, do the following:
- Choose Monthly/yearly from the schedule drop-down list:
-
- Specify job start schedule in the appropriate fields.
- Specify the time when the job should be started in the Starting field.
- Specify the end time for the job in the Ending field. If the job has not completed by the time specified, the job will be stopped.
- Choose a time zone which should be used for the job start and end times from the time zone drop-down list.
- Select the days of the week during which the job will be started.
Periodic Backup
To run a job multiple times per day, do the following:
- Choose Run periodically from the schedule drop-down list and then choose a time periods from the appropriate fields:
-
- Specify the time when the job should be started in the Starting field.
- Specify the end time for the job in the Ending field. If the job has not completed by the time specified, the job will be stopped.
- Choose a time zone which should be used for the job start and end times from the time zone drop-down list.
Chained Job
To run the job after a previous one has completed, do the following:
- Choose Run after another job from the schedule drop-down list and set the options as follows:
- After the job: select a job after which the current job will be started
- Run this job: Choose whether to run the current job immediately after the previous one has completed or specify a delay
- After successful runs: If selected, the job will run if the previous one has completed successfully
- After failed runs: If selected, the job will run if the previous one has failed
- After stopped runs: If selected, the job will run if the previous one has been stopped
資料來源: 原廠NAKIVO(https://www.nakivo.com)此篇文章之權利屬於NAKIVO所有